Raley Field Downtown Baseball Stadium - Sacramento, CA

general contractor

J.R. Roberts

developer

River City Baseball Association, L.L.C.

square feet

103,300

value JD2 brought to project

JD2, Inc. was faced with the monumental task of taking a 16 week delivery schedule and 14 week erection schedule down to only 6 weeks for steel on site and 3 weeks for erection, in order to make opening day. We not only succeeded in that effort, but also had the ability to provide some significant value engineering through the process that saved time and money.

more info

please click images for larger view

client
testimonial

"Their innovative ideas and 'can do' spirit helped complete the project in what would have been considered a nearly impossible schedule in good weather, let alone in the middle of winter. Their unique abilities provided us value and tremendous speed, allowing us to "play ball" on time."

Tag Gebhart, Senior Estimator